Water Distribution for Wilayt Al Hamra

时间:2018-07-07 17:26:45 来源:领航丝路 点击数:258

  • GENERAL INFORMATION 

    OWNEROman Public Authority for Electricity & Water
    MASTERPLAN PROJECT (PARENT PROFILE)-
    LOCATIONAl-Hamra, Dakhiliyah Governorate, Oman
    STATUSMain Contract Bid
    SECTORWater Pipeline, Transmission, Water
    CONTRACT TYPEDesign Build (DB)
    ONSHORE/OFFSHOREOnshore
    GREENFIELD/BROWNFIELDGreenfield
    PROGRESS

     

    0%

    BUDGET VALUE$100m
    CONTRACT VALUE-
    NET VALUE$100m
    AWARD DATEOctober 2018
    COMPLETION DATEJanuary 2020
    LAST UPDATED ONJuly 2018

  • DESCRIPTION & SCOPE

    Public Authority for Electricity and Water is planning to carry out a new transmission and distribution network installation for the water supply system in Al Hamra Wilayat. (Tender No: PAEW/HO/PDD80/2017) 

    The US$100 million project includes the following: 

    A. Pipeline 

    1. Construction of 85km D.I pipe network with 100mm to 500mm 
    2. Construction of 180km HDPE pipe network with 110mm to 315mm 

    B. Storage Reservoirs 

    1. Construction of three large storage reservoir of 6,000m3 

    C. Design and Build packages: 

    1. Construction of pumping station 
    2. Construction of PS-01, Al Hamra 
    3. COnstruction of BPS-5 station 
    4. Laying a 7km new pipeline from existing Al Hamra reservoir to PS-01 
    5. Laying a 4km new pipeline from existing Al Hamra reservoir to new Al Hatt reservoirs 
    6. Construction of 2km bypass connection between the existing pipeline and the new transmission pipeline 
    7. Construction of associated facilities